Tiles at Leisurepark Balga - Replacement

The Aquatic concourse tiles at Leisurepark Balga have reached the end of their usable life and are due to be replaced.

The new tiles will have a higher slip resistance rating to reduce slipping incidents at the facility and this replacement is scheduled to start on Monday 19 February 2018.

A full replacement will occur through a staged approached and has been broken into ten stages, Removal of  the existing tiles is carried out overnight and re-tiling occurring during the day, to ensure that there is no loss of service.

The entire replacement is expected to take four months with each stage being 1-3 weeks in length.

During stage 1 patrons will be required to use the gym access gates, then walk past the crèche to access the pool.


A map of the staged approach to the replacement is shown above.


Featured Posts
Recent Posts
Archive
Search By Tags
No tags yet.
Follow Us
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
  • Facebook Social Icon
  • Twitter Social Icon
  • Instagram Social Icon
bottom of page