Tiles at Leisurepark Balga - Replacement
The Aquatic concourse tiles at Leisurepark Balga have reached the end of their usable life and are due to be replaced.
The new tiles will have a higher slip resistance rating to reduce slipping incidents at the facility and this replacement is scheduled to start on Monday 19 February 2018.

A full replacement will occur through a staged approached and has been broken into ten stages, Removal of the existing tiles is carried out overnight and re-tiling occurring during the day, to ensure that there is no loss of service.
The entire replacement is expected to take four months with each stage being 1-3 weeks in length.
During stage 1 patrons will be required to use the gym access gates, then walk past the crèche to access the pool.
A map of the staged approach to the replacement is shown above.